Haverfordwest interchange: Next stage of £19m project backed
The second stage of building Haverfordwest’s near-£19m transport interchange has been backed, with senior councillors hearing it could cost the council more to not support it.
The transport interchange, which includes an integrated bus station and construction of a new multi-storey car park, is part of a wider series of regeneration projects in the county town.
The total cost of the scheme in the approved budget is £18.881m, £1.987m from Pembrokeshire County Council; the remainder, £16.894m, from an already-awarded Welsh Government grant.
To date, £3.425m has been spent on advanced works, including the demolition of the old multi-storey car park and a temporary bus station.
Members of Pembrokeshire County Council’s Cabinet, meeting on April 22, were recommended to approve the award of the Stage 2 construction contract for the Haverfordwest Transport Interchange.
The report for members listed two simple options for Cabinet, to authorise the award of a contract, recommended, or to not.
For the latter it warned: “It is envisaged Welsh Government will withdraw the funding awarded and the council would need to repay grants received to date; £10.322m has been received to date of which £3.376m has been offset against expenditure.”
It added: “Cost to cease this project could cost PCC more in terms of grant repayment and any capital work required to make good. PCC match contribution for the project is forecast as £1.987m of the £18.881m.”
Planning permission for the interchange was granted in 2022, with a temporary bus station constructed that year and the old multi-storey building demolished in 2023.
That year, members of the county council’s Cabinet agreed a temporary car park will be sited on the demolished remains of the old multi-storey car park until the Haverfordwest Public Transport Interchange – delayed as no compliant tender had been found at the time – is built.
Speaking at the meeting, Deputy Leader Cllr Paul Miller said: “The interchange is an important part of the regeneration of Haverfordwest, it will not regenerate Haverfordwest on its own, it is part of a wider process. The alternative to us being engaged is we simply allow it to decline and fail.”
He said the interchange was about “making it easier to visit Haverfordwest,” making parking provision “really straightforward, making it easy and convenient as possible”.
Cllr Miller said not progressing with the scheme would risk the grants already obtained, meaning the council could potentially foot the bill for costs to date, at a greater level than progressing.
He said the cost options were a near-£2m subsidised council involvement for the whole scheme or the £3m-plus spent to date if the scheme was ended, which would leave the car park as it is now.
“It’s pretty reasonable that if they give us the money and we don’t build a transport interchange they’ll be looking for that money back,” Cllr Miller said.
He said previous figures from parking revenue – back in 2019 – amounted to £100,000 a year; and could be expected to at least double on a “like-for-like” basis following the increase in parking charges.
Members, after a private and confidential session over the actual contract details, agreed to proceed with the scheme, awarding the contract to Kier Construction Western and Wales.
Education
Milford Haven School issues heatwave update as temperatures soar
MILFORD HAVEN SCHOOL has thanked pupils and staff for the way they have supported one another during the current heatwave.
The school said cooperation and care across the school community had been greatly appreciated.
With tomorrow (Jun 25) forecast to be the hottest day of the current spell, pupils are being asked to come prepared by bringing plenty of water, wearing sunscreen, and staying as protected from the sun as possible.
Pupils will also be permitted to wear their PE kit to help keep cool.
The school said it will continue to monitor the situation closely and take all necessary steps to prioritise the safety and wellbeing of pupils and staff.
Business
Main Street Music to close retail shop as owner focuses on handmade guitars
A POPULAR Pembrokeshire music shop is changing the way it operates, with Main Street Music confirming it will no longer trade as a retail shop from September 1.
The business said there will be an immediate 15% sale on all stock, but stressed that Main Street Music is not disappearing completely.
The owner said the decision had been made “with a heavy heart”, adding that the shop’s closure as a retail outlet would be a loss for Pembrokeshire as the county’s last professional guitar dealership.
He said his long-term passion had always been making musical instruments, something he had done since his teenage years, later receiving scholarships and a fellowship for his studies.
After college, he was given the opportunity to buy the business at the age of 24.
He said: “I have had an amazing time running this shop, giving it everything I’ve got, met some wonderful people and sold some incredible guitars.”
Although the business itself remains successful, he said tighter retail margins, dealership pressures and rising costs had made it difficult to grow in a way that would allow him to employ others and spend more time in the workshop.
The shop will eventually reopen as an appointment-only workshop and showroom for handmade guitars and repairs.
Current repair work will continue on a case-by-case basis by appointment only.
Main Street Music thanked customers for their support over recent years, saying the owner was proud of where the shop had been taken.
Caption:
Main Street Music will close as a retail shop from September 1, but will continue as an appointment-only workshop and showroom for handmade guitars and repairs.
News
Crackwell Street set to reopen after five-month closure
ROADWORKS linked to structural repairs at Goscar House in Tenby are nearing completion, with Crackwell Street expected to reopen to through traffic today (Wednesday, June 24).
Scaffolding has now been removed from the property, with contractors carrying out a general clearance of the area.
The road has been closed for around five months while structural repair work has been taking place.
Local residents, businesses and visitors are expected to welcome the reopening, with Crackwell Street forming an important route through the town.
Pembrokeshire County Council has indicated that, all being well, the road will reopen later today.
Gareth Davies, of Gareth Davies Photography Tenby, said it was “good to see the removal of scaffolding today and general clearance on the property”.
He added that locals and visitors would be “so pleased” to see the road open once again.
Photo caption:
Clearance work: Contractors at Crackwell Street, Tenby, as scaffolding is removed from Goscar House (Pic: Gareth Davies).
-
Crime6 days agoMilford Haven man jailed for breaching domestic violence protection order
-
News6 days agoCrash on Freeman’s Way causes school-run chaos across Haverfordwest
-
Health4 days agoWoman jailed assaults on police, harassment and XL Bully possession
-
Crime4 days agoMilford Haven woman spared jail despite string of shop thefts
-
Crime6 days agoPortfield Gate man faces careless driving allegation after Tufton crash
-
Community3 days agoThe gentle giant behind the tattoos
-
Local Government6 days agoPembrokeshire faces accessible housing shortage as 403 people wait for homes
-
News7 days agoBrexit at 10: How Britain was sold a dream that cost us dearly