Climate
£40m-plus Newgale road scheme to come under public spotlight
PEMBROKESHIRE proposals for a £40m-plus road realignment scheme at flood-hit Newgale, and a far cheaper alternative scheme, are to come under the spotlight at full council next week.
Newgale was hit hard by flooding following storms in early 2014 storms, and later by Storm Dennis in 2020.
In 2014 it even saw a visit by the-then Prime Minister David Cameron following the storms.
A public consultation – through agent AtkinsRéalis – was launched earlier this year ahead of a formal Pembrokeshire County Council application to Pembrokeshire Coast National Park for Phase 1 of the Newgale Coastal Adaptation Project, which would see the development of a new inland section of road with bridge over Brandy Brook some 2.3km inland, to replace the coastal section of A487 at Newgale that will be closed and removed, among other works.
Varied claims have been made about the cost of this scheme, from £20m upwards, some even saying it could cost as much as £60m, with millions spent on consultation fees to date.

An alternative scheme has been proposed by STUN – Stand Up for Newgale, who have previously said the public has been misled over the need for the new Newgale bypass.
STUN’s far cheaper alternative proposes a section of the shingle bank at Newgale be realigned 10-12 metres seaward leaving an over-wash barrier between it and the A487 to capture any pebbles and sea water.
In a question, on behalf of Solva Community Council, to be heard at the July 17 meeting of Pembrokeshire County Council, community council chair Gareth Chapman will ask: “The topic of the road diversion at Newgale has been in the news quite a lot recently and it has become apparent that there has been an alternative scheme proposed by the Newgale Community group STUN.
“This proposal has been demonstrated to Solva Community Council and appears to be an under £1m proposal with up to 85 years lifespan compared to the conservative £40m-plus estimate for the PCC proposal.”

The question says “hardly anyone wants this major change in Newgale,” adding: “PCC’s proposal is to counter for road closures that rarely happen and, even then, require little expense to restore the pebble bank. It should also be remembered that on several occasions, flooding at Newgale occurs because the river outlet is blocked preventing water from the valley escaping and not as a result of a high tide or storm.
“It is acknowledged that climate change and coastal issues at Newgale may eventually in many years force a change in the highway arrangements at Newgale but it is felt that all efforts should be made to retain the character of the village and iconic views for as long as possible.
“Given the huge amount of public money that is proposed to be spent, and could well be better spent on other more pressing issues, would Pembrokeshire County Council commit to thoroughly examining the alternative proposal as WelTAG [Welsh Government Transport Appraisal Guidance] suggests they should, and also fully take on board the overwhelming public opinion regarding the future of Newgale?
“Secondly if Pembrokeshire County Council have already given this alternative scheme full consideration, will they also commit to providing their written comments on the alternative scheme to Solva Community Council within 14 days of this meeting?”
The question will be responded to at the meeting.
Climate
Chris Packham backs Carmarthen ‘nature crisis’ climate screening
BROADCASTER and environmental campaigner Chris Packham has backed a free public screening in Carmarthen aimed at encouraging local discussion about the climate and nature crisis.
The People’s Emergency Briefing will be shown at St Peters Civic Hall, Carmarthen, on Friday, May 22, at 7:00pm.
The screening will be followed by a facilitated community discussion involving residents, local leaders and invited decision-makers.
The event forms part of a UK-wide programme intended to help the public and policymakers better understand the risks posed by climate change and biodiversity loss.
The film follows the National Emergency Briefing held at Westminster Central Hall in November 2025, where more than 1,200 MPs, peers and leaders from business, culture, faith, sport and the media gathered to hear evidence from leading experts.
The briefing, introduced by Chris Packham CBE, examined the impact of climate and nature breakdown on food security, public health, infrastructure, the economy and national security.
It has since been adapted into a 50-minute public film, which launched nationally in April and is now being screened in communities across the UK.
Chris Packham said: “I’d encourage people everywhere to attend a screening of The People’s Emergency Briefing.
“It creates exactly the kind of honest local conversation we now urgently need, both about what these changes mean where we live, and about what we can do together to address them.”
Organisers say the Carmarthen event comes at a time of growing local concern over flooding on the rivers Towy and Gwili, as well as biodiversity loss linked to pollution incidents.
After the film, those attending will be invited to take part in a structured discussion about the issues raised and what they may mean locally.
Local MPs, councillors and other influential figures have also been invited.
Philip Hughes, one of the organisers, said: “This is about creating space for people to come together, look at the evidence, and begin a more open and informed conversation about what it means for our community.
“It is also about how we can support the bolder action now called for by the science, which will also do so much to improve lives, as the film explains.”
Tickets for the Carmarthen screening are free, but advance registration is encouraged.

Climate
Welsh windfarms to power major construction materials firm
A MAJOR construction materials company has signed a long-term deal to use renewable energy from Welsh windfarms as part of efforts to cut carbon emissions.
Energy firm RWE has agreed a 15-year contract to supply electricity to Breedon Group plc, which operates sites across Great Britain producing materials including concrete, asphalt and cement.
Under the agreement, RWE will provide around 70 gigawatt hours of renewable electricity each year from its windfarm portfolio.
The power will initially come from the Gwynt y Môr offshore windfarm, about 24km off the coast of North Wales in the Irish Sea. From 2033, supply will switch to the Brechfa Forest West onshore windfarm in Wales.
The electricity will support the production of key building materials, helping Breedon reduce emissions linked to its energy use in a sector widely regarded as difficult to decarbonise.
RWE said the agreement highlighted the role renewable energy can play in helping heavy industry move towards lower-carbon operations.
Olaf Lubenow, head of commodity solutions at RWE, said: “This agreement underlines our commitment to supporting the construction materials sector on its journey towards a more sustainable future.
“By supplying renewable electricity from our wind portfolio, we are helping to reduce the carbon footprint of Breedon’s operations.”
Breedon said the deal would also provide long-term energy stability while supporting its wider sustainability plans.
Donna Hunt, the company’s sustainability director, said the agreement marked “a meaningful step forward”.
She said: “It secures long-term energy supply and helps accelerate the reduction of emissions from our operations.”
The company has set targets to cut emissions across its business by more than 20% by 2030 and to reach net zero by 2050.
The agreement reflects a growing trend of major industrial firms turning to renewable energy to help meet climate targets while managing rising energy costs.
Business
Pembroke Power Station National Grid shutdown power plans
A CALL to site specialist diesel generators at Pembroke Power Station to help keep the lights on in the event of a National Grid shutdown has been lodged with county planners.
In a screening application to Pembrokeshire County Council, RWE Generation UK PLC, through Ove Arup & Partners Ltd, wants to site up to six containerised diesel generators, diesel storage tank(s) and electrical connections at Pembroke Power Station, Pwllcrochan, near Pembroke.
The application site is within the site of the existing Pembroke Power Station, a combined-cycle gas turbine (CCGT) station which began commercial operation in September 2012, with a gross consented capacity of about 2,199 megawatts electric (MWe), replacing the previous oil-fired power station which operated for almost 30 years and was decommissioned in 1999.
A supporting statement says, subject to confirmation, it is considered to comprise permitted development, the scheme “a standalone plant, with its own fuel supply, capable of starting up, operating and shutting down independently from the power station”.
It adds: “It is required only in an emergency to maintain plant status and keep the power station operationally ‘ready’ in the event of a total or partial shutdown of the National Grid system. It is not required for the normal operation of the power station and does not extend its capacity, which remains as already consented, therefore it is not considered a change or extension.”

On need, it says it is mandatory that all electricity generators of over a megawatt have to adopt a new minimum standard of asset resilience; power stations “must be capable of restoring demand on the National Grid electricity transmission system in the event of a total or partial shutdown of the National Grid system”.
“The Power Station does not currently meet this new asset resilience standard, therefore new back-up power, control philosophy and on-site services that support site critical systems enabling the power station to remain ready to operate must be implemented.
“RWE is required to install a new enhanced emergency site auxiliary solution (diesel generators and diesel storage tanks) at the power station for resilience against the failure of the interconnected electricity distribution network into which it is normally connected in order to satisfy the Grid Code requirements by the mandated implementation deadline of December 31, 2026.
“RWE will make operational and fuelling provision, within its new resilience design at Pembroke power station of up to 120 hours, in order to provide capability to a slightly enhanced standard known to be valued by the National Energy System Operator (‘NESO’) in certain emergency network scenarios.”
It says construction is hoped to start in July 2026, lasting approximately nine to 12 months, the main part across the summer months.
The call will be considered by county planners at a later date.
-
News21 hours agoBaby in critical condition after Fishguard emergency
-
Community6 days agoDogs removed after welfare concerns at Milford Haven property
-
Crime7 days agoPembrokeshire hairdresser avoids prison after pub assault
-
Crime3 hours agoMilford motorist disqualified for drug-driving
-
Business7 days agoHandcrafted garden furniture built to last across Pembrokeshire
-
Charity7 days agoRow erupts at Spitfire museum after Reform poster displayed at charity premises
-
Community7 days agoCancer patients targeted with parking fines outside Haverfordwest support centre
-
Crime6 days agoTwo men bailed after Fleming Crescent burglary report