Connect with us
Advertisement
Advertisement

News

Fishguard Marina plans a step closer

Published

on

Screen Shot 2016-06-07 at 11.07.27PEMBROKESHIRE COUNTY COUNCIL’S Planning and Rights of Way Committee has given its consent to the removal and variation of a number of conditions to allow for a phased development to take place at Fishguard Harbour.

The development at the Harbour would include a marina, residential apartments and retail facilities.

The decision made by Council on Tuesday (May 17), allows for a phased approach of reserved matters and would not result in the loss of planning control.

Cllr Brian Hall said that the development would be a massive asset to Fishguard.

Mr Andrew Patterson said: “The Focus of our written submissions related to Condition 6 for the Phasing Plan and our belief that the detailed Phasing Plan should be submitted and made accessible to the public before any other variation of the conditions was considered.

“Condition 6 had not been included within the application itself – which caused us some disquiet. However, the Director of Development’s report to this Committee outlines the mechanism to be put in place for Condition 6, and the related conditions and we welcome these assurances, and request that they will be clearly stated in any planning approval given.

“We fully endorse the recommendation made in Para 6.11 to the effect that a separate discharge of conditions application for Condition 6 should be submitted to the Local Planning Authority, and we request that it will be consulted in a way similar to the current application.

“Assuming that in principal approval is given to this current application, the assurance that the submission of the Phasing Plan will be the first submission to be made by the applicant against this new planning approval is welcomed.

“However, we are still concerned about certain wording within this current application in relation to overall infrastructure issues.

“The original approval given in 2014 is very unusual. It essentially gave permission for the creation of two new pieces of land – one with outline schemes presented for residential development, and a marina and boat yard; and the second – the Development Platform – whose use will be determined by a future application.

“However the major infrastructure issues such as access onto The Parrog, and for foul water disposal, will be common to both platforms.

“The suggestion in the proposed amendments is that the details for each Phase affecting the first piece of new land, will be developed in accordance with the timetable set out within the Phasing Plan.

“It is therefore essential that access on to the Parrog and other major infrastructure issues are identified within the Phasing Plan as the first of the conditions that needs to be discharged.

“If this is not done, there will be a risk of further civil engineering cost and disruption at some time in the future.

“In relation to civil engineering, we believe that is essential that the discharge of both Condition 13 (Construction Traffic Management Plan)(CTMP) and Condition 15 (Construction Environmental Management Plan)(CEMP) are identified within the Phasing Plan in parallel with the access and infrastructure conditions.

“We believe that the Phasing Plan should include a detailed time-tabled Programme, highlighting the key breakpoints in the delivery, so that progress can be monitored, and also so that critical path decision points can be identified.

“We therefore request a revision to the wording of Condition 6 to ensure that the Phasing Plan includes considerations for both platforms of the full access, and infrastructure considerations, and also the CTMP and the CEMP.

“Once this Phasing Plan and programme has been determined there will be greater transparency of the whole development and its consequences.

“Finally, we believe that the development is reaching a stage when closer engagement and consultation with a group representing local resident and business interests would be useful, and would lead to more informed and productive discussion of the evolving plans.”

Cllr Myles Pepper said: “This is such a large scale and very sensitive application and the director has removed it from the scheme of delegation in light of the sensitive issues raised by the developer.

“This allows for phased submissions and this would not create any loss of planning control and this was a fear that had been expressed locally that things were being done which they had no control over.

“I’m also encouraged by comments from Fishguard and Goodwick Town Council who have no adverse comments.

“The Town Council, and I quote from the report, wishes you to know that they believe there is no danger to the community with regards to the variances and therefore, they have no adverse comments to make with regards to the application as a whole.”

Cllr Pat Davies said: “I have no hesitation in approving these recommendations. This has been a long time coming and there has been huge public consultation. My community welcome this marina.”

Cllr Keith Lewis added that they needed to put a message out to the developer to get them to start the project as soon as possible because the marina was very important to the north of the county.

The application was unanimously approved by councillors.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Community

County Hall to offer space for community banking

Published

on

A CALL for Pembrokeshire County Council to potentially change its banking arrangement with Barclays, after it closed its Haverfordwest branch has been turned down, but County Hall is to offer space for community banking.

Barclays Bank, on the town’s High Street, is to close on May 10.

The council has had a banking services contract with Barclays since 2013.

Councillor Huw Murphy, in a notice of motion heard by Pembrokeshire County Council’s Cabinet meeting of April 22, asked the council to review its banking arrangements with Barclays following the announced closure.

e said the loss of a branch “not only impacts upon town centres and businesses but also disproportionately impacts the elderly who are less likely to embrace on-line banking options”.

A report for Cabinet members said, in terms of the impact on Pembrokeshire residents, Barclays has said that it is “not leaving Haverfordwest and [will] continue to provide face-to-face support for those who need it” via community locations.

Two options were presented to Cabinet: to retender the banking services contract, and, the favoured, to work with Barclays to ensure a community location is set up in Haverfordwest.

Members heard the costs associated with moving to a new banking service provider could be in excess of £50,000.

For the second, favoured option, members heard Barclays was in discussions with the council about a location for potential community banking.

Cabinet Member for Corporate Finance Cllr Alec Cormack, after outlining the risks in the report for members, and moving the notice be not adopted, said he had “considerable sympathy” with Cllr Murphy’s notice.

He told councillors there was a glimmer of light for banking arrangements in the county, with an agreement now signed for two ground floor rooms at County Hall, Haverfordwest, to be used for community banking.

From April 25, the rooms will be available on Wednesdays, Thursdays, and Fridays, members heard.

Cabinet Member for Planning & Housing Delivery Cllr Jon Harvey also said he had “a lot of sympathy” for the motion, adding: “It’s excellent news a deal has been struck to occupy the ground floor rooms three days a week; hopefully this will mitigate, to a certain amount, the closure.

“If we can work with the respective banks to get a community-type approach let’s move forward.”

Continue Reading

News

Haverfordwest interchange: Next stage of £19m project backed

Published

on

The second stage of building Haverfordwest’s near-£19m transport interchange has been backed, with senior councillors hearing it could cost the council more to not support it.

The transport interchange, which includes an integrated bus station and construction of a new multi-storey car park, is part of a wider series of regeneration projects in the county town.

The total cost of the scheme in the approved budget is £18.881m, £1.987m from Pembrokeshire County Council; the remainder, £16.894m, from an already-awarded Welsh Government grant.

To date, £3.425m has been spent on advanced works, including the demolition of the old multi-storey car park and a temporary bus station.

Members of Pembrokeshire County Council’s Cabinet, meeting on April 22, were recommended to approve the award of the Stage 2 construction contract for the Haverfordwest Transport Interchange.

The report for members listed two simple options for Cabinet, to authorise the award of a contract, recommended, or to not.

For the latter it warned: “It is envisaged Welsh Government will withdraw the funding awarded and the council would need to repay grants received to date; £10.322m has been received to date of which £3.376m has been offset against expenditure.”

It added: “Cost to cease this project could cost PCC more in terms of grant repayment and any capital work required to make good. PCC match contribution for the project is forecast as £1.987m of the £18.881m.”

Planning permission for the interchange was granted in 2022, with a temporary bus station constructed that year and the old multi-storey building demolished in 2023.

That year, members of the county council’s Cabinet agreed a temporary car park will be sited on the demolished remains of the old multi-storey car park until the Haverfordwest Public Transport Interchange – delayed as no compliant tender had been found at the time – is built.

Speaking at the meeting, Deputy Leader Cllr Paul Miller said: “The interchange is an important part of the regeneration of Haverfordwest, it will not regenerate Haverfordwest on its own, it is part of a wider process. The alternative to us being engaged is we simply allow it to decline and fail.”

He said the interchange was about “making it easier to visit Haverfordwest,” making parking provision “really straightforward, making it easy and convenient as possible”.

Cllr Miller said not progressing with the scheme would risk the grants already obtained, meaning the council could potentially foot the bill for costs to date, at a greater level than progressing.

He said the cost options were a near-£2m subsidised council involvement for the whole scheme or the £3m-plus spent to date if the scheme was ended, which would leave the car park as it is now.

“It’s pretty reasonable that if they give us the money and we don’t build a transport interchange they’ll be looking for that money back,” Cllr Miller said.

He said previous figures from parking revenue – back in 2019 – amounted to £100,000 a year; and could be expected to at least double on a “like-for-like” basis following the increase in parking charges.

Members, after a private and confidential session over the actual contract details, agreed to proceed with the scheme, awarding the contract to Kier Construction Western and Wales.

Continue Reading

Charity

RNLI prepare for summer with medical training exercise in Pembrokeshire

Published

on

RNLI lifeguards from the north Pembrokeshire team, volunteers from St Davids RNLI and St Davids Coastguard Rescue Team came together at Whitesands beach on Thursday (18 April), for a multi-agency medical training exercise. Pembrokeshire RNLI lifeguards and St Davids volunteer lifeboat crew took part in a multi-agency medical training exercise alongside St Davids Coastguard Rescue Team in preparation for the upcoming summer season.

The Coastal Medicine programme was set up six years ago at the suggestion of clinicians from Hywel Dda University Health Board. The aim of the programme is train lifeguards, lifeboat crews and HM Coastguard teams in working collaboratively when responding to medical incidents on the coast.

Clinicians from Hywel Dda work with RNLI staff to design exercises simulating mass-casualty incidents on land and afloat. The exercises allow lifeguards, lifeboat crews and Coastguard teams to practise and test their rescue response and casualty care.

The simulated incident at Whitesands involved a medical incident at sea leading to a boat going out of control and ploughing through a group of swimmers causing multiple injuries. RNLI lifeguards responded to casualties on the beach while St Davids inshore and all-weather lifeboat crews dealt with the situation at sea. St Davids Coastguard Rescue supported RNLI colleagues as they would in a real-life scenario.

In total there were six casualties to treat, all of whom were given the immediate medical care by the teams on scene. As in a real-life scenario, they were then prepared to be handed over to the care of the Ambulance Service.

Roger Smith, RNLI Area Lifesaving Manager said: ‘The scenario was based on a real-life incident, it’s so important that we train in dealing with challenging situations.

‘The RNLI lifeguards, lifeboat crew, and the Coastguard rescue team worked really well together collaborating together to achieve the best possible result.

‘The feedback from all the participants was really positive, and our medical colleagues were very complimentary about the competence shown and the inter-agency co-operation.

‘This scenario training gives confidence to our lifeguards and lifeboat crews, and ensures the teamwork and communication is already in place ready for real-life incidents.’

Martin Charlton, an RNLI lifeguard in north Pembrokeshire said:

‘Last night’s exercise was a great opportunity for me and my colleagues on the lifeguard team to upskill ahead of the summer season.

‘We regularly attend incidents in the season that require a multi-agency response. These scenarios are a brilliant opportunity to prepare for the the most challenging situations.

‘The team and I thoroughly enjoyed the exercise and feel better prepared for the season as a result.

‘It’s always a pleasure working alongside the Coastguard rescue team and the lifeboat as one crew.’

Continue Reading

News14 hours ago

Haverfordwest interchange: Next stage of £19m project backed

The second stage of building Haverfordwest’s near-£19m transport interchange has been backed, with senior councillors hearing it could cost the...

News3 days ago

20mph U-turn: Some roads will return to 30mph following public outcry

IN a recent shift in policy, Transport Secretary Ken Skates announced that some roads in Wales will revert to a...

News4 days ago

Police issue update on the search for Luke, missing from Pembroke Dock

POLICE have made the difficult decision to end the search for Luke, following a joint decision by all the agencies...

Entertainment5 days ago

NoFit State Circus set to thrill Pembrokeshire this summer

NoFit State Circus is set to captivate Pembrokeshire once again this summer, as they bring back their thrilling big top...

News6 days ago

Search for missing teenager Luke continues at Pembroke Dock

THE SEARCH for the missing 19-year-old, Luke, continues unabated into its fourth day, with efforts increasingly centred around the waterways...

Crime1 week ago

Estate agents admit health and safety failings following fatal market incident

WEST WALES estate agents J J Morris have appeared before Pembrokeshire law courts charged with failing to discharge general health,...

Crime1 week ago

Pembroke man sent ‘grossly offensive and disgusting’ message to sister

A DISTRICT Judge has described how a Pembroke man sent a ‘disgusting, appalling and grossly offensive’ message to his sister...

News1 week ago

Dragon LNG ‘monitoring’ scrap car blaze in Waterston

A BLAZE has broken out at the Waterston Car Dismantler’s business in Waterston, Milford Haven. Dragon LNG which is situated...

News2 weeks ago

Major search in the area of The Cleddau Bridge and Hobbs Point

A MULTI-AGENCY rescue response was initiated first thing on Saturday following reports of a person in difficulty in the area...

News2 weeks ago

Newgale pub fire: Cause undetermined, but ruled accidental

THE MID and West Fire and Rescue Service (MAWWFRS) has recently concluded its investigation into the fire that devastated the...

Popular This Week