LNG’s turbine scheme of national significance
A £14.3m scheme for up to three near 500-foot high wind turbines to provide green energy for Pembrokeshire’s Dragon LNG site will eventually decided by Welsh Government, county planners heard.
Milford Energy Limited (MEL), a sister company of Dragon LNG Limited, is seeking permission for an onshore wind farm and associated equipment, infrastructure and ancillary works at Dragon LNG Meadow, Milford Haven adjacent and to the south of the Waterston Dragon LNG terminal.
It is proposed that the minimum capacity of the development would be 10 megawatts, but could be as high as 12.6-13.5MW, depending on turbine model, with up to three turbines of up to 149.9 metres in height, again depending on the final model selected.
The Dragon liquefied natural gas (LNG) terminal provides gas for use by millions of commercial and residential UK consumers, with the capacity to supply up to 10 per cent of the UK’s needs.
Dragon LNG owns the main part of the site where the wind turbines are proposed to be located and will lease the land to MEL.
A supporting statement says the proposal “forms an important part of the carbon reduction strategy for the terminal as the purpose of the proposed wind turbines (together with the existing co-located solar farm) is to provide a direct supply of renewable electricity, primarily to reduce the terminal’s carbon intensity as a key component in Dragon’s ambition to become a Net Zero terminal by 2029”.
The proposed turbines are expected to provide up to 39 per cent of Dragon LNG’s energy needs; any excess electricity generation can be exported to the grid.
A report for members of the county council’s planning committee, meeting on December 5, stated: “This application is one to be determined by Welsh Ministers and not the Local Planning Authority (LPA) due to the relevant threshold enshrined in The Developments of National Significance (Specified Criteria and Prescribed Secondary Consents) (Wales) Regulations 2016 (as amended) being exceeded; in this case the installed generating capacity being greater than 10 megawatts.”
Members of Pembrokeshire County Council’s planning committee, meeting on December 5, were recommended to note the contents and conclusions of the adopted Local Impact Report (LIR) associated with the development rather than make a formal decision.
Chair of the committee, Cllr Jacob Williams said the format of application was the first of its type received by the committee, following changes to the council’s constitution.
Previously, such responses to applications of national significance would not come before the committee, members were told.
The application to note the LIR was moved by Cllr Brian Hall and supported by committee members.
Business
Ferry Terminal ‘extremely busy’ due to ongoing Holyhead closure
PEMBROKE DOCK Ferry Terminal has been experiencing significant congestion today as ferry services remain under immense pressure following the closure of Holyhead Port earlier this month.
The disruption, caused by storm damage, has rerouted ferry traffic through Pembrokeshire, leading to long queues and crowded facilities at the terminal.
The Herald can confirm that it has been very busy today with cars, lorries, and foot passengers queuing in large numbers. Staff are working tirelessly to manage the influx, directing vehicles and assisting passengers as they prepare to board the heavily booked ferries.
A spokesperson for the Port of Milford Haven said: “We are working closely with ferry operators and local authorities to ensure traffic flows as smoothly as possible, but the sheer volume of vehicles is causing unavoidable delays.”
Travelers are being urged to arrive early for their sailings and to remain patient as the terminal operates at full capacity.
Both Stena Line and Irish Ferries have increased capacity on their Pembrokeshire routes, deploying larger vessels, including the Stena Adventurer and the MV James Joyce, to handle the surge in demand.
From our position at the terminal, our photographer has captured photos showing long lines of vehicles, groups of foot passengers carrying luggage, and port staff coordinating efforts to ease congestion.
Authorities are advising non-essential travelers to consider rescheduling their journeys where possible and to monitor updates from ferry operators closely.
(Photos: Martin Cavaney/Herald)
Business
52 homes to be built in Roch as scheme gets final sign-off
THE FINAL stage of approval for a near-£10m Pembrokeshire residential development of 52 homes has been given the go-ahead.
Back in April, members of Pembrokeshire County Council’s planning committee backed an application by Wakefield Pembrokeshire Ltd for the development, which includes four one-bed affordable housing units, on land near Pilgrims Way, Roch.
18 objections to the scheme were received, raising concerns including an “inadequate” affordable housing level, it being a high density development for a rural area, a loss of green space, the size of some of the homes, and pressures on existing services and facilities, and fears it may lead to an increase in second homes.
Nolton & Roch Community Land Trust (N&RCLT) has raised its concerns about a lack of affordable homes at the development, calling for a 20 per cent affordable homes element, as recommended by policy.
An officer report for members, recommending conditional approval, said: “It is apparent that the proposed development is not fully policy compliant, insofar as it cannot deliver the indicative 20 per cent affordable housing sought [by policy].
“However, a substantial positive social impact will arise through the provision of housing, including four one-bed affordable housing units, in meeting identified needs for both market and affordable housing.
“Financial obligations identified to mitigate adverse impacts arising from the proposed development cannot be met in full. However, [policy] acknowledges that in such circumstances contributions may be prioritised on the basis of the individual circumstances of each case.”
Speaking at the meeting, agent Gethin Beynon said the project had a “significant economic value” of around £10m, and the local applicant had “a sense of stewardship to the local community,” offering affordable housing and community infrastructure towards highways and education.
Approval was delegated to the council’s head of planning to approve the application, subject to the completion of a Section 106 planning obligation, making community financial contributions.
The Section 106 agreement was recently agreed, with the application now formally approved.
Business
World of engineering and welding SPARCs interest in Ysgol Harri Tudur’s female learners
AN EVENT hosted by Ledwood Engineering gave girls from Year 8 and 9 at Ysgol Harri Tudur first-hand experience of the world of engineering recently.
Engineering is a booming sector in Pembrokeshire with a high demand for skilled workers in exciting career pathways associated with the development of low carbon and renewable energy industry and the Celtic Freeport.
The young women heard from industry experts on the importance of engineering in Pembrokeshire, and had hands on experience using a welding simulator, at the company’s Pembroke Dock site.
The learners are part of the County’s SPARC (Sustainable Power and Renewable Construction) initiative aimed as inspiring and empowering young females to consider careers in science, technology, engineering and mathematics (STEM) pathways where females are under-represented in the workforce.
SPARC is funded through an alliance comprising Blue Gem Wind, Ledwood Engineering, Port of Milford Haven, RWE Renewables, Pembrokeshire County Council, Pembrokeshire College and the Swansea Bay City Deal.
Mrs Laura Buckingham, SPARC practitioner at Ysgol Harri Tudur said: “Our learners had a fantastic experience at Ledwood Engineering. They were given lots of advice by industry experts on the different career options and pathways within the engineering sector.
“They appreciated the opportunity to ask their questions and found the session very informative. Having the chance to trial their welding skills on the simulator was an experience they continue to talk about and has definitely piqued their interest.”
Poppy Sawyer, Year 8 SPARC learner added: ‘It was a really good trip. Talking to the different people there has helped me know more about the jobs we could get which will be very useful when making choices for my future.”
“They helped us a lot by giving us lots of information. We were able to look around and try welding. It was really fun,” added Tianna Marshall, Year 8 SPARC learner.
The Regional Learning and Skills Partnership also launched its Explore Engineering interactive website at the event.
-
News1 day ago
Ferry accident causes delay on new Dublin-Fishguard route
-
Top News6 days ago
Pembrokeshire man jailed after repeatedly punching pregnant wife
-
Top News5 days ago
Police investigate dogs seen persistently chasing sheep on Pembrokeshire airfield
-
News7 days ago
Dyfed-Powys Police launches attempted murder investigation
-
News7 days ago
Heroes of the storm: How Council workers rallied during rare red wind warning
-
Top News6 days ago
Milford man dealt ‘persistent’ blows on girlfriend after urinating in flat
-
News6 days ago
Engine room fire caused by loose fuel pipe connection previously flagged
-
News6 days ago
Children seen kicking and ‘egging’ doors near Pembrokeshire train station in early hours