Connect with us
Advertisement
Advertisement

News

Flood victims round on Port Authority

Published

on

UNHAPPY homeowners from Havens Head and Lower Priory vented their anger and frustration at Pembrokeshire County Council and Milford Haven Port Authority at a special meeting of a Council scrutiny committee this week.

Chair Rob Summons convened the extraordinary meeting of the Council’s Services Overview and Scrutiny Committee for Tuesday (July 21), after a report into devastating floods which struck the hamlets near Milford Haven in November 2018.

Cllr Summons’ wanted to allow residents, who did not get the report in time for the Committee’s June meeting, to contribute to the Committee’s discussions.

Neither the Port nor the Council is prepared to accept any responsibility for the flood. The report’s content focussed, therefore, on possible preventative measures to avoid a repeat of them.

CAUSES IDENTIFIED
The report concluded a combination of a rapidly rising watercourse, silting in the pills, high water levels in them after heavy and sustained rainfall, the low capacity of the culverts, and high tide levels all contributed to the floods.

The report notes the drainage system’s complexity and the poor condition of much of its infrastructure.

The local authority reviewed a report prepared for the Port Authority by civil engineering firm Atkins last June. Atkins’ report recommended the Port Authority should significantly increase the width of the culverts to cope with increased volumes of water run-off.

At the time, several councillors asked if, as the Port Authority claims, the existing culverts are adequate and fit for purpose, why Atkins recommended their size should be increased to handle three times the volume of water for which they’re currently designed.

LOCAL FURY
Ian Bannister, who lives in Lower Priory addressed Tuesday’s meeting.

He said critical assumptions made in the report about the extent of the previous flooding were flawed. Mr Bannister said in the week before the events of November 7-9, 2018, the pills were already full to overflowing. Water in the Lower Priory Pill was at such a level, Ian Bannister said, the footpath leading to Havens Head was inundated.

He also told committee members that repeated requests to open the sluice gates to reduce the flooding’s severity were ignored and one of the sluice gates supposed to release water from the pills had been broken for ten years and was only now being repaired.
Neither the Port Authority nor Council Officer Darren Thomas was having any of it.

Rocking back and forth in his chair, hands behind his head, and staring at the ceiling while answering questions was not a good look for Mr Thomas, in particular. He gave the unfortunate impression of not being much interested in anything Mr Bannister had to say.
Metaphorically patting the Council on the back for its response to the flooding appeared confused by Darren Thomas with a proactive role in preventing it.

Appearing on behalf of the Port Authority, Chair Chris Martin and Chief Executive Andy Jones, determinedly stuck to the line that it wasn’t them, guv.

Acutely aware of the litigation risk it faces if it concedes even an inch, the Port Authority’s approach is to brickbat any suggestion of contributory fault on its part. Conditions of the culverts were less than ideal but had no effect on the flooding. A valve in the system which didn’t work properly had nothing to do with the backflow of water. A failure to drain the pills over the preceding days, of little or no effect. Defective sluices and failure of water measurement equipment, nothing to see there.

 

Emotional moment: Ian Bannister from Lower Priory clearly upset by the damage caused (Pic: Herald)

REPORT DID NOT PLAY BLAME GAME
While Ian Bannister might have felt like he was banging his head against a brick wall trying to get to the heart of the matter, getting to the heart of the matter was something the Capita report didn’t address and an issue which its authors were not asked to address.

Capita was not asked to assess who, if anyone, was to blame; presumably, in case they could and were able to apportion it.

Sticking to the narrow technical criteria of their brief, Capita conducted flood modelling, produced options based on that modelling, costed those options, and provided conclusions accordingly.

And it was the conclusions which took some swallowing; especially the one recommended to the Council.

Although the report recognises engineering options could be used to help alleviate the flood risk it notes the options for doing so are expensive and would require further justification to the Welsh Government to secure funding.

Capita’s economic assessment says a flood alleviation scheme would be difficult to justify over and above what it describes as ‘Business as Usual’.

That option involves sustaining the current Welsh Government Flood and Coastal Erosion Risk Management arrangements including routine maintenance or inspections of flood and coastal defence systems, or doing the (bare) legal minimum where there is a statutory requirement to continue them.

It accepts flood risks affecting several residential and commercial properties but does not take into account rising sea levels, the increased frequency of extreme weather events, or the continuing development at Milford Haven Docks.

As Ian Bannister pointed out, the area of land on which the Port Authority wants to build a car park for its proposed hotel development was flooded by raw sewage washed down from the pills in November 2018. That does not appear to have been factored into the Port’s hotel plan, dealt with in the drainage assessment for the development and relayed to the Council’s Planning Committee.

The report concludes, however, the potential exists for a flood alleviation scheme in Milford Haven as there are economic benefits of undertaking one. It recommends further work is to cost a scheme and refine one’s economic viability.

COUNCILLORS TAKE AIMAT PORT AUTHORITY
When the time came for councillors to respond to the report and what they had heard in response to residents’ concerns, questions became even more pointed.

Cllr Viv Stoddart said she wanted to look at potential solutions.

Referring to a recommendation in the report, which suggested replacement of the existing Havens Head culvert section with a slightly larger circular concrete culvert of and building a new section to discharge into the Port, she asked for confirmation of the works estimated costs.
Responding Council Engineer Emyr Williams confirmed the cost estimate was £3.4m but added he regarded that as an optimistic cost because of the poor state of the made-up ground. She asked whether some form of joint-venture would be possible.

Based on her local knowledge of the areas affected, Viv Stoddart drew councillors’ attention to the content of a sentence in the report’s conclusions: ‘It can be said in summary that the culvert is the primary cause of flooding in Havens Head and Lower Priory’. Mrs Stoddart said it was her view and other residents’ views going back many years that the culverts were inadequate and could not cope with periods of very heavy rain.

Cllr Stoddart drew attention to the extent of backfilling at Goose Pill, going back as far as the 1970s and assumptions made in an appendix presented to the meeting which said were unsubstantiated assertions. Viv Stoddart said, in her view, liability rested with the Port Authority and its predecessors in title over the land it now owned. She added to rely on insurers declining to pursue the Port Authority as evidence the Port Authority was not liable ignored the litigation risk and cost of pursuing proceedings against it.

Cllr Mike Stoddart suggested the backfilling of the pills was a substantial issue. Backfilling the pill, he said, inevitably increased the pressure on the culverts and reduced their effectiveness and moving water. He added the original culverts were much shorter and their increased length was necessitated by the effects of backfilling which reduced the pills’ ability to handle excess water. Mike Stoddart compared the effect of backfilling reducing the capacity of the lake to sinking six concrete blocks in a bath and watching it overflow in short order.

Cllr Stoddart drew members’ attention to an alteration made to both the direction of the Havens Head culvert and a reduction its width. Emyr Williams said he agreed the hydraulics of the system were ‘less than satisfactory’. Mike Stoddart suggested that work be commissioned to see if the diversion of the Haven Head culvert to discharge directly into the Docks would – at least – partly address the flood risk.

He pointed out the Port Authority had done very well out of its ownership of the land, as had the previous Milford Docks Company. The Port Authority, he said, should not be allowed to ignore problems which arose as a result of its actions or inaction.

COMMITTEE WANTS MORE INVESTIGATIONS
Cllr Rhys Sinnett raised an ‘easy win’ the report identified, which suggests artificially and permanently lowering the pills’ basins, to create an increased storage volume.

Capita’s representative, John Greenier, said that option was part of a suite of solutions which could have a considerable cost.

Cllr Stephen Joseph said had it not been for the Fire Service pumps removing 14,000 litres of water a minute from Havens Head, the buildings there would have been inundated at an extraordinary cost. He pointed out the Fire Service were not there as an insurance policy for a landowner which failed to act to protect its own property. He observed that modern practice built-in flood attenuation as standard and infill, as took place in the past, would not happen now.

Cllr Joseph added the report needed to go back to Cabinet to find out what money was available for further investigations and the ‘business as usual’ recommendation should be rejected.

Supporting the suggestion, Cllr Di Clements said the Cabinet needed to put its money where its mouth is and commission a fresh look at the problems.

Cllr John Preston said a number of agencies were involved and each was passing the buck. He said ‘business as usual’ was what created the problem in the first place.

Cllr Rob Summons moved a recommendation that the Committee send the report to Cabinet for further action and examination of options.
The Chair’s recommendation carried unanimously.

Community

Major progress in plan to reduce tidal flooding in Cardigan

Published

on

PLANS to mitigate tidal flooding in the Strand area of Cardigan, West Wales, have reached a key milestone with the appointment of specialist consultancy firm Binnies to lead the Detailed Design Phase of the Cardigan Tidal Flood Scheme.

Flood wall to protect homes and businesses

The scheme, spearheaded by Natural Resources Wales (NRW), involves constructing a flood wall along the riverbank, extending from Gloster Row Carpark to Cardigan Bridge. The wall is expected to reduce tidal flood risks for around 90 homes and businesses, significantly improving safety and community resilience.

Binnies, a consultancy renowned for expertise in flood risk management, will oversee critical aspects of the project, including the design of construction materials and ensuring resilience against future climate challenges. The design phase will also explore opportunities to enhance the local environment and create new community spaces.

NRW collaboration with Binnies

Paul Isaac, NRW’s Project Executive for the scheme, said: “This is a pivotal moment for the Cardigan Tidal Flood Scheme. We are thrilled to continue our collaboration with Binnies, whose expertise – along with ours – will enable us to make good progress through the Detailed Design Phase. Together, we are confident in producing a design that not only addresses the immediate flood risks but also creates long-term value for the community and environment.”

Timeline and next steps

The Detailed Design Phase is expected to be completed by early 2026, after which a planning application will be submitted to Ceredigion County Council. Upon approval and securing funding, construction is projected to begin later in 2026.

This milestone follows the October publication of the proposed flood wall outline, further demonstrating NRW’s commitment to protecting Cardigan from tidal flooding. The project is funded by the Welsh Government, reflecting its broader focus on enhancing climate resilience across Wales.

Flood risk awareness campaign

With 1 in 7 properties in Wales at risk of flooding and extreme weather becoming more frequent due to the climate emergency, NRW urges residents to take proactive steps:

  • Check flood risk by postcode on NRW’s website.
  • Sign up for free flood warnings, available in Welsh and English.
  • Be prepared when flooding is forecast.

Stay informed

A digital newsletter has been launched to keep residents and stakeholders updated on the scheme’s progress. Sign up for updates here: https://bit.ly/CTFSNewsletter.

This project is a vital step toward safeguarding the future of Cardigan, ensuring the town is better protected against the increasing risks posed by tidal flooding.

Continue Reading

News

Neyland councillor defends actions following petition for resignation

Published

on

A STATEMENT has been issued by Cllr Mike Harry in response to a petition calling for his resignation, which was handed in during the Neyland Town Council meeting on Monday (Jan 13). The petition, organised by Mrs P Percival-Maxwell, accuses Cllr Harry of making inappropriate remarks and creating division within the council.

In his detailed statement, Cllr Harry rejected the allegations, describing the petition as “factually incorrect” and part of a targeted effort to discredit him and further destabilise the council.

Cllr Mike Harry

Cllr Harry explained that his email, which is at the centre of the controversy, was a response to what he described as “insulting and threatening” messages from fellow councillors Brian Rothero, Steve Thomas, and David Devauden. He clarified that the term “degenerates” referred specifically to those individuals, who he accuses of relentless bullying and harassment of the Town Clerk, not Neyland residents.

He also pointed out that the “constituents” referred to in the petition are, in fact, a group of five individuals who attended an unauthorised meeting and whom he alleges are regulars at a local pub owned by Cllr Rothero.

Cllr Harry claimed that the ongoing behaviour of Cllrs Rothero, Thomas, and Devauden has rendered the council dysfunctional and unable to serve the people of Neyland effectively. He described their actions as consistently disruptive, highlighting the negative impact on the Town Clerk and the council’s ability to progress key matters.

“I’d simply had enough and had to finally call it out for what it is,” he stated, noting that his email was directed at a total of eight individuals who, in his view, show no interest in the council’s proper functioning.

Cllr Harry, who has served on Neyland Town Council for nearly 20 years, emphasised his dedication to the community and its residents. “The interests of the residents of Neyland have always been paramount to me,” he said. He expressed frustration over the current tensions within the council, calling the situation “particularly difficult and insulting” and not reflective of why he became a councillor.

The petition has deepened divisions within Neyland, with some residents supporting Cllr Harry’s defence and others standing by the petition’s call for his resignation. The issue highlights broader concerns about the council’s internal dynamics and its ability to address key issues for the community.

Continue Reading

Charity

Two shouts and nine hours at sea for Angle RNLI

Published

on

ANGLE All-Weather Lifeboat was requested to launch at 9:15pm on Wednesday night, 15th of January to assist a 25 meter commercial landing craft with 8 persons onboard taking water in St Brides Bay. The vessel was under tow from a tug following a grounding and salvage operation.

St David’s All-Weather Lifeboat were on scene with their salvage pump having already been transferred onboard, and Little Haven Inshore Lifeboat had also attended during the evening.

Angle Lifeboat made best speed to the area and arrived on scene 30 minutes later and soon had their salvage pump transferred onto the casualty vessel to assist with keeping the water ingress at bay.

Both lifeboats began to escort the tow but whilst west of Skomer Island, however a change of plan, and in light of the vessel still taking water a plan was made to alter course and proceed to Broad Haven Beach with a view to beach the vessel to prevent it sinking.

The lifeboats then spent the next few hours escorting the tow and providing safety cover. Upon arrival off Broad Haven, and with the tidal state not right to beach the vessel the lifeboats stood by whilst pumping efforts continued.

At 3:15am, with the situation now improving, St David’s Lifeboat was released and returned fo station. Not long after at 4am, with the water ingress now under control, Angle Lifeboat was subsequently stood down after the master confirmed he was content with the vessels condition.

Just over 3 hours before, at 5:30pm the crew were paged to assist a 10 meter pleasure vessel that had suffered electrical failure off the VPOT oil terminal on the Milford Haven waterway.

As the crew were already at station preparing to launch on exercise, the crew were soon underway and with the casualty vessel not long after.

Following a quick assessment the vessel was soon underway and with tow towards Neyland Marina.

Once off the entrance to the marina, the vessel was transferred into an alongside tow and placed safely alongside a pontoon within the marina.

With no further assistance required the lifeboat was stood down and the crew returned to their usual Wednesday night exercise.

Continue Reading

News2 days ago

Landslides close section of Pembrokeshire coastal path once again

A SECTION of a south Pembrokeshire beach-side coastal path has been closed once again after a number of landslips in...

Community2 days ago

Stricken vessel now off Broad Haven as pollution experts stand-by

A dramatic turn of events has seen the survey vessel KMS Terramare redirected to Broad Haven, where it is set...

News3 days ago

Housing plans for former Penally asylum seeker camp

THE EARLY stages of plans for a potential housing scheme at a Pembrokeshire military training camp, controversially used to house...

News3 days ago

Survey vessel stranded at Newgale beach prompts RNLI response

A 24.5-METRE survey vessel, the MTS Terramare, found itself in a precarious situation after becoming stranded on Newgale Beach on...

Health4 days ago

Cancer patients face long waits for diagnosis and treatment in Wales

A REPORT released by Audit Wales has revealed that cancer care in Wales continues to struggle with significant delays in...

Crime5 days ago

Father of baby girl killed in Tenby incident says its been like a ‘horror movie’

A SIX-MONTH-OLD baby girl has tragically died after her pram was struck by a car in a multi-storey car park...

Crime5 days ago

Ex-prison officer exposes failures and mismanagement at HMP Parc

A FORMER prison officer has come forward with allegations of systemic failings at HMP Parc in Bridgend, claiming that neglect,...

Charity5 days ago

Charity seeks homes for hens destined for slaughter in Pembrokeshire

A CHARITY dedicated to saving ex-laying hens from slaughter is appealing to the public to help rehome 139 chickens at...

Community5 days ago

Urgent action needed to protect Wales’ natural resources, says NRW report

NATURAL RESOURCES WALES (NRW) has published its interim State of Natural Resources Report 2025 (SoNaRR), urging immediate, collective action to...

Community7 days ago

Engineering work to bring major disruptions across local rail network

TRANSPORT FOR WALES, in partnership with Network Rail, has announced a comprehensive programme of engineering works across the South West...

Popular This Week