Politics
Haverfordwest airport could be leased out to make it ‘cost-neutral’
![](https://pembrokeshire-herald.com/wp-content/uploads/2023/07/airport-1.jpg)
HAVERFORDWEST airport could be leased out as part of plans to make the council-run facility, currently forecast for a £119,000 deficit, cost-neutral to the authority.
Last year, Pembrokeshire County Council’s Cabinet, members heard the financial position at the council-supported Haverfordwest/Withybush airport deteriorated in 2022/23, with an out-turn position for 2022/23 of £238,000.
At the March 26 meeting of Pembrokeshire County Council’s services overview and scrutiny committee members received a report on the airport, stating: “In the financial year 2022-23 the airport operated at a cost to the council in the region of £238,000, and, whilst highly valued, this level of spend cannot be justified in the current financial climate when placed against many of the statutory services the council has to deliver.
“Following an extensive review of the operations of the airport, this loss has been considerably reduced, however the airport continues to operate at a loss, which this financial year 2023/24 is forecast to be £119,000.”
The report lists reasons for the halving of this deficit, including: increased profit margin on fuel £40,000; increased landing fees £7,000; reduction in staff training £8,000; reduction in equipment and equipment maintenance costs £10,000; and a reduction in one off costs of hedges and sewers £53,000.
Five options were presented to members as ways of making the airport cost-zero: retain the airport with a drive towards becoming cost neutral; close the airport tower; sell the airport on a freehold or long leasehold basis; lease the airport to a current stakeholder and established aviation company; and finally to advertise the airport to let on the open market.
Of the options, the first, could generate around £15,000 a year extra through a number of opportunities, the report said, but added that significant capital investment was needed in the facility, including ground lighting close to the end of its useful economic life, which could cost £400,000-£500,000, along with a corroded fuel storage tank, needing to be replaced at a cost of £200,000.
Some informal conversations have taken place around the favoured option, to lease the airport to a current stakeholder, members heard.
“Although at this stage detailed conversations have only been had with one party, the opportunity to lease will also be offered to other existing stakeholders,” the report stated.
“It is also likely that an existing stakeholder might be a ‘special purchaser’ who would pay more than the market as their existing interests will also benefit.
“Following these discussions, it seems there is a potential that the council would be able to agree a lease of the airport to an experienced and well-established aviation company who is an existing stakeholder with a good track record.”
It finished: “This option would make the airport cost neutral to the council from the day the lease is signed whilst also ensuring that an operational airport remains for Pembrokeshire to benefit from.”
Councillor Di Clements proposed that option be backed, seconded by Cllr Rhys Jordan, with members unanimously approving the option.
A final, more detailed recommendation is to be presented to the council’s Cabinet at a future meeting.
If approved, the lease would be dealt with under the delegated authority of the Assistant Chief Executive.
News
Community asked for views on allocation of new St Davids homes
![](https://pembrokeshire-herald.com/wp-content/uploads/2024/07/Glasfryn3-scaled-e1721980963591.jpg)
THE FIRST phase of Pembrokeshire County Council’s Glasfryn housing development in St Davids is progressing well with the second phase also underway.
The development being built by GRD Homes Ltd, began in November 2023, with a first phase completion date of Winter 2024 looking hopeful, ahead of the scheduled plans.
The first phase consists of seven properties, including a mixture of one and two bedroom bungalows
As completion draws closer the properties will be advertised via Pembrokeshire Choice Homes.
Ahead of this, the Council’s housing team will be holding community engagement on the 13th August 2024 at the Ty’r Pererin Centres, Quickwell Hill, St Davids, SA62 6PD, 5pm-7pm.
This will be a chance for officers to liaise with the local community about the allocation process for these properties.
Glasfryn’s second phase is well underway, with the initial groundwork already completed. This phase includes a further 11 two bedroom bungalows, with a completion date in late 2025.
These bungalows will meet the latest Welsh Government’s Development Quality Requirement, and will be energy efficient, built to EPC A specification and include solar panels to help tenants with running costs.
The Glasfryn development is funded in partnership with Welsh Government.
Cabinet Member for Housing Cllr Michelle Bateman said: “We are really keen to work with the community on a local lettings policy for these new properties, as we have done for our developments in other parts of the County.”
If you have any queries please email the Customer Liaison Team on [email protected], phone them on 01437 764551, or visit Housing’s Facebook page.
Business
Legal call to stop £6m expansion of holiday park still ongoing
![](https://pembrokeshire-herald.com/wp-content/uploads/2024/06/heritage-park-expansion.jpg)
A LEGAL request to overturn a Pembrokeshire County Council-granted approval for a £6m expansion of a south Pembrokeshire holiday park is still ongoing despite a previous announcement it had been turned down, county planners heard.
Back in February, Pembrokeshire planners were informed a legal challenge to a November 2023-granted application for works at Heritage Park, Pleasant Valley/Stepaside had been launched.
The holiday park scheme had previously been backed twice by county planners after a ‘minded to approve’ cooling-off period was invoked as it was against repeated officer recommendations to refuse.
The controversial scheme by Heritage Leisure Development (Wales) Ltd includes the installation of 48 bases for holiday lodges, a spa facility at a former pub, holiday apartments, a café and cycle hire, equestrian stables, a manège and associated office, and associated works.
It is said the scheme, next to the historic remains of the 19th century Stepaside ironworks and colliery, will create 44 jobs.
Officer grounds for refusal, based on the Local Development Plan, included the site being outside a settlement area.
Along with 245 objections to the current scheme, Stepaside & Pleasant Valley Residents’ Group (SPVRG Ltd) – formed to object to an earlier 2019 application which was later withdrawn – also raised a 38-page objection, with a long list of concerns.
A failed legal challenge to try and overturn a council decision to approve three separate planning applications at Heritage Park was launched in 2021 by SPVRG Ltd, which failed in early 2022; the council awarded costs of £10,000 despite external legal fees paid totalled £34,000 plus VAT.
At the June meeting of Pembrokeshire County Council’s planning committee members were told the recent judicial review call by SPVRG Ltd had been refused by the high court, the grounds put forward “not considered to be reasonably arguable”.
Committee chair Cllr Simon Hancock said a council request for SPVRG Ltd to pay costs incurred by the county council in defending the claim had now been submitted.
Following that, at the July planning meeting, in his chair’s announcement, Dr Hancock gave a clarification on the position.
“I can advise that whilst the application for judicial review was refused by the High Court Judge on May 31, 2024, the appellants have challenged this decision.
“This matter is listed for a renewal hearing, and accordingly the legal challenge is still in progress; I’m hoping that’s a clarification from the announcements I made back in June.”
Responding to the clarification, Trish Cormack of SPVRG Ltd pointed out it was not “an appeal,” adding: “Firstly, we are ‘requesting the decision to be reconsidered at a hearing,’ which is a bit less dramatic than ‘challenging the decision’.
“Secondly, the claim remains open for seven days after the decision on the papers in expectance of you requesting the hearing, and the form 86B comes attached to the decision with the case number already filled in for you. This is just part of the process for a judicial review. If the Judge really thought there were no merits to the case, he was free to issue a ‘without merits refusal’.
“That would have ended the claim there and then. The only way to resurrect it would have been to take it to the appeal court. But he didn’t.
“Thirdly, the announcement makes it sound like our ‘challenge’ had happened after their previous announcement, whereas in fact we only had seven days from May 31 in which to make the request, so they knew the moment we did (June 7) because we had to simultaneously email it to the court, PCC and the developer’s agent. So, they knew full well that there would be a renewal hearing.”
Farming
Farm building scheme near Lawrenny given go-ahead by planners
![](https://pembrokeshire-herald.com/wp-content/uploads/2024/07/Lawrenny_Church-e1721925610409.jpg)
AN APPLICATION for a storage building at a south Pembrokeshire farm, made by a family member of an officer on Pembrokeshire County Council’s planning service, has been given the go-ahead by the authority’s planning committee.
In an application recommended for approval at the July 23 meeting of the authority’s planning committee, Laura Elliot sought permission for the erection of an agricultural storage building at Tedion Farm, a dairy farm near Lawrenny.
The application had been brought to committee, rather than being delegated to planning officers, due to the family connection.
The farm, near to the Pembrokeshire coast National Park border, comprises 270 milking cows and dairy heifer replacements kept on the farm comprising land over 138 hectares. The farm is mainly down to grass and the cows are paddock grazed in order to utilise grass efficiency.
No objections had been received from local community council Martletwy.
A report for members said: “The application seeks consent for the erection of agricultural storage building. The erection of an agricultural building will be used to store stay, hay and farm machinery.
“The building would be located within the existing farm complex, to the north-east of the site, adjacent to the main farm dwelling. The building will measure 18 metres in length by 13.6 metres in width, with a pitched roof height of 5.71 metres.”
Approval was moved by Cllr Alistair Cameron, seconded by Cllr Brian Hall.
-
Education5 days ago
Milford Tesco worker achieves Oxford dream and lands top legal job
-
Crime4 days ago
Haverfordwest man admits having nearly 1000 child and animal images
-
Crime4 days ago
Youth set to appear in court over serious sexual offences
-
Crime4 days ago
Police investigating after man injured during altercation in cemetery
-
Education4 days ago
Pupils delight in ice cream treat from Pembrokeshire’s number one van
-
Crime4 days ago
Town centre ‘stinking of skunk’ as police strip cannabis farm
-
Crime3 days ago
Fag-butt police court summonses spark debate in Pembrokeshire
-
News6 days ago
Proposal to give firefighters a council tax discount to go to Cabinet