Connect with us
Advertisement
Advertisement

Climate

National Grid battery storage scheme site visit defeated by one vote

Published

on

A CALL to defer a scheme for a south Pembrokeshire national grid-connected electrical battery storage facility close to Pembroke Power Station after concerns were raised that it had no actual connection in the plans was defeated by just one vote.

In an application before the July meeting of Pembrokeshire County council’s planning committee, the scheme by Sirius EcoDev (Lambeeth) Ltd for the installation of a Battery Energy Storage System (BESS), associated infrastructure including a 132kv substation and engineering works on land east of the Greenlink Converter Station, near Pembroke Power Station, was recommended for conditional delegated approval.

A report for planners said the BESS compound of 46 battery containers and 23 power conversion systems would have a 40-year lifespan and the “proposed point of connection to the Grid would be approximately 300m to the north of the BESS compound, albeit that this does not form part of the application”.

The scheme would provide electricity storage equivalent to supplying over 20,819 homes, the report said.

The application described the need for the BESS infrastructure, the report said: “Renewable energy supply from wind and solar is intermittent with a fluctuating supply to the Grid. As renewable energy provision increases, there is a risk of increased energy supply fluctuations and therefore increased need for facilities that store energy so that supply can be regulated. BESS do not create carbon emissions or generate electricity but provide a balancing mechanism drawing electricity (charging) when levels on the network are above that of demand.

“When levels of electricity on the grid are below that of demand the electricity stored in the batteries can be fed back (discharged) onto the network to meet the demand. BESS provides sub-second response times, so offer a reliable solution to a number of the Grid’s balancing issues thus supporting the development and deployment of low carbon intermittent energy technologies.”

Concerns about the scheme in its current form were raised at the July meeting by local councillor – and county council chairman – Steve Alderman, who later called for a site visit to view the application.

Cllr Alderman raised concerns about potential safety issues and said the current plans would have “a site full of batteries and no connection to charge them”.

Cllr Alderman added: “It does bother me; we have a site, in between two powerful electricity sites, it has no planned connection.

“I’m really not happy about this at all, there’s 132kv between two lines, that seems to be a serious safety issue.”

He later said he was “all for building storage solutions,” adding “the future generations are going to need it”.

Calling for a site visit, he said: “It bothers me, I would normally be all for this. We have a site, but what we don’t have is a facility to use these batteries, both for charge and for discharge, it has no way of charging or discharging, I don’t get this; I would like to see it deferred until we have a line that is useable.”

Cllr Jordan Ryan told members they should think “very carefully” in voting to pass the scheme when “there’s all these questions up in the air”.

“Cllr Alderman has got some very valid questions; I think we should be backing the local member,” Cllr Ryan added.

Members heard details of the cable route had been removed from a previous application to that presented to committee.

The site visit call was defeated by seven votes to six, members later agreeing to delegated approval for the plans.

Business

Impala Terminal Milford Haven hydrogen gas pipeline approved

Published

on

A CALL for a 1.5km hydrogen gas pipeline in Pembrokeshire in connection with a previously granted scheme for green energy production has been given the go-ahead by county planners.

In an application to Pembrokeshire County Council, Zurich-based MorGen Energy Ltd, previously known as H2 Energy Europe, sought permission for a 1.5km six-inch 10-bar low-pressure hydrogen pipeline and associated Above Ground Installation at the Impala Terminal, Milford Haven to the South Hook Liquid Natural Gas (LNG) Terminal.

A supporting statement through agent Fisher German said the scheme crossed both Pembrokeshire County Council and the national park authorities, with a similar application before that authority.

It added: “The proposals form part of the West Wales Hydrogen project, where planning permission was granted on October 6, 2023, for the development of a new 20MW hydrogen production facility at the Impala Terminal (formerly Puma Energy) in Milford Haven.

“The approved hydrogen production facility which uses electrolysis to split water into hydrogen and oxygen, where the oxygen is a by-product of the process.  The hydrogen production plant will produce 1,875 tons of hydrogen per year. Hydrogen will be distributed via high pressure vessels (40 ft. containers) to various customers in the closer vicinity, opening the hydrogen market to a large variety of customers.

“Hydrogen will also be distributed to the South Hook LNG Terminal and it is proposed that this will be via a new six-inch 10-bar hydrogen pipeline. The option to supply hydrogen to the South Hook LNG terminal via high pressure hydrogen containers was dismissed due to safety considerations at the terminal.

“This application therefore seeks planning permission for a section of below ground hydrogen pipeline within the jurisdiction of Pembrokeshire County Council, which comprises the north part of the route from the hydrogen plant at Impala to the South Hook LNG Terminal, alongside an AGI at the Impala Terminal.”

An officer report recommending approval said: “The proposal is to construct a below ground hydrogen pipeline and an Above Ground Installation (AGI).  The southern part of the proposed pipeline is within the jurisdiction of the Pembroke Coast National Park Authority – a separate planning application has been made to PCNPA.

“The hydrogen pipeline would supply South Hook LNG terminal with low carbon hydrogen from a new hydrogen production facility at the Impala Terminal that benefits from planning permission.

“The application states that ‘the South Hook LNG Terminal will use the hydrogen to partially decarbonize their site, namely their Submerged Combustion Vaporisers (SCVs) by blending hydrogen into the natural gas stream’.”

The application was conditionally approved.

Continue Reading

Climate

Wales-wide groups call for fair and democratic transition to Net Zero

Published

on

COMMUNITY groups from across Wales have united behind a new Charter calling for a fundamental overhaul of how renewable energy developments are planned and approved.

The Charter for a Just Transition to Net Zero has been launched by an alliance of grassroots and environmental organisations who say current planning arrangements favour large-scale energy developers at the expense of local communities.

Campaigners argue that residents affected by wind farms, energy parks and grid infrastructure are being left without adequate information, influence or access to independent advice, while developments are approved piecemeal without proper consideration of cumulative impacts.

The groups say the planning system is failing to give communities a meaningful voice, despite the long-term consequences for landscapes, heritage and wellbeing.

Dr Jonathan Dean, spokesman for the Campaign for the Protection of Rural Wales (CPRW), said Wales must address climate change without sidelining rural communities.

“Wales must tackle climate change, but not by excluding the very communities who live in and care for these landscapes,” he said. “This Charter sets out a credible and democratic path forward, and we are urging all political parties to adopt its principles ahead of the 2026 Senedd election.”

Concerns raised in the Charter include a lack of transparency around proposed schemes, limited opportunities for early engagement, and the growing pressure on communities facing multiple overlapping energy developments.

Jenny Chryss, campaign lead at ReThink, said communities across Wales were being overwhelmed by the scale and pace of proposals.

“Right now, Wales is seeing multiple energy schemes coming forward with little regard for cumulative impacts, environmental damage or community wellbeing,” she said. “This Charter is about the basics: honesty, accountability and decisions that put people first.”

The Charter calls for a series of reforms, including early and clear disclosure of proposed developments, direct engagement with affected communities, and fair access to independent legal and technical advice.

It also calls for a pause on new approvals until cumulative impacts are properly assessed, alongside stronger protections for landscapes, heritage and public wellbeing.

Supporters say Wales can meet its climate targets while maintaining democratic accountability and public trust, warning that failing to do so risks undermining confidence in the transition to Net Zero.

The Charter has been backed by community and environmental groups from across the country, including organisations representing areas facing significant pressure from large-scale renewable energy proposals.

CPRW, founded in 1928, said the document offers a practical route to delivering climate action without sacrificing rural communities or public confidence in the planning system.

Continue Reading

Climate

Yellow weather warnings issued for Pembrokeshire as ice and snow forecast

Published

on

Travel disruption likely as council activates emergency shelter measures

TWO yellow weather warnings for ice and snow have been issued for Pembrokeshire over the weekend, with hazardous conditions expected to affect travel across the county.

The first Met Office warning is in force until 10:00am on Saturday (Jan 3), with a second warning running from 3:00pm on Sunday (Jan 4) until 12:00pm on Monday (Jan 5). The alerts follow an earlier warning that was in place from midnight until midday on Friday (Jan 2).

Forecasters say icy conditions and snowfall could lead to delays to bus and rail services, while drivers are being urged to plan ahead and allow extra time for journeys, particularly on untreated rural roads and higher routes across north Pembrokeshire and the Preseli Hills.

The Met Office said between 1cm and 3cm of snow is likely in parts of the county, with higher ground potentially seeing accumulations of 5cm to 8cm. Wintry showers are expected to become more frequent overnight, with icy patches forming where surfaces remain untreated.

Pedestrians have also been warned that pavements and cycle paths could become treacherous or impassable, especially during the early morning and evening hours.

In response to the cold conditions, Pembrokeshire County Council has confirmed it will activate its Severe Weather Emergency Protocol (SWEP) from Friday (Jan 2) through to Sunday (Jan 4). The measure allows emergency accommodation to be provided for known rough sleepers during periods of extreme weather.

The council is urging members of the public to report anyone sleeping rough so they can be offered emergency shelter over the weekend.

Continue Reading

Crime12 hours ago

Man jailed after samurai sword brandished in Pembroke Dock street brawl

15-month sentence after “ugly” disturbance left members of the public fearing for their safety MICHEL VALMONT has been jailed for...

Education1 day ago

Pembrokeshire Learning Centre placed in special measures following Estyn inspection

PEMBROKESHIRE LEARNING CENTRE has been placed in special measures after inspectors raised serious concerns about standards and leadership at the...

Crime2 days ago

Father jailed for 35 years after baby hurled at television

Court hears infant suffered catastrophic, life-changing injuries after violent attack in Ceredigion home A COURT has heard how a two-month-old...

News2 days ago

Former Tory chancellor Zahawi defects to Reform UK

NADHIM ZAHAWI has defected from the Conservative Party to Reform UK, becoming Nigel Farage’s highest-profile political recruit to date and...

News2 days ago

Ancient New Year celebrations still ring true in hidden corner of Pembrokeshire

WITH New Year celebrations safely packed away with the tinsels and baubles for another 12 months, a quiet corner of...

News4 days ago

Search of River Teifi continues as police scale back multi-agency response

Family kept informed as officers urge public to avoid unsafe independent searches A POLICE search of the River Teifi in Cardigan will continue over...

Crime4 days ago

Man pleads guilty after £150k drugs haul found in Pembroke traffic stop

Routine police check led to discovery of cocaine and cannabis in car boot A MAN has pleaded guilty after a...

Education5 days ago

Council refuses to reveal cost of replacing roof on nine-year-old Tenby school

A primary school built in 2016 is facing a full roof replacement after years of leaks and structural deterioration —...

Local Government5 days ago

Council re-approves £14.3m contract for Haverfordia House redevelopment after costs rise

Delays, inflation and expired contractor pricing blamed as scheme timetable slips to 2027 PEMBROKESHIRE COUNTY COUNCIL has re-approved a £14.3m...

News5 days ago

Storm Goretti causes widespread disruption across Pembrokeshire

SEVERE winter weather brought by Storm Goretti caused widespread disruption across Pembrokeshire on Thursday evening ( Jan 8 ), with...

Popular This Week