Council refuses to reveal cost of replacing roof on nine-year-old Tenby school

Published

on

A primary school built in 2016 is facing a full roof replacement after years of leaks and structural deterioration — but Pembrokeshire County Council is refusing to disclose how much the work will cost taxpayers.

A NEWLY built Pembrokeshire school is facing a full roof replacement less than a decade after opening, with Pembrokeshire County Council refusing to disclose how much the work will cost the public.

Tenby Church in Wales VC School, a 3–11 English-medium primary school with an additional Learning Resource Centre provision, was completed in 2016. However, just a few years later, reports of water ingress began to emerge, with the situation worsening to the point where more than 500 temporary supports are now holding up parts of the roof.

The council has confirmed that it holds multiple condition and engineering reports relating to the roof dating back to January 2020, and that the issue has been discussed at Cabinet level on more than one occasion.

However, in a response to a Freedom of Information request, Pembrokeshire County Council has refused to disclose the total estimated cost of repairs, temporary works, or a planned full roof replacement, citing commercial sensitivity.

The council has also declined to release any correspondence between itself, the Welsh Government and the school’s governing body relating to warranties, insurance claims, or liability for the roof defects, again relying on exemptions under the Freedom of Information Act.

The Herald received the FOI response on Friday, January 9, 2026. In it, the council confirmed that while reports and assessments exist — and have been presented to Cabinet — key financial and contractual details are being withheld from public view.

The Herald previously reported in November that Cabinet members approved a £75,000 feasibility budget to explore options for tackling the ongoing roof leaks, including the possibility of a complete roof replacement. At that time, councillors were told that repeated water ingress had resulted in a weakening of the structure and components within the roof construction.

As part of urgent health and safety measures, the council installed 510 ‘acro’ props to support vulnerable roof areas and fully closed the Early Years and Playgroup wing. In 2024, the school’s solar photovoltaic array was also removed on engineer advice to reduce loading on the roof.

A Cabinet report stated that the favoured option is the replacement of the entire roof, a course of action that would require a comprehensive decant strategy to relocate pupils while works are carried out.

Presenting the findings of the feasibility study, the Cabinet Member for Education and Welsh Language, Cllr Guy Woodham, acknowledged the seriousness of the situation, telling members that the wellbeing of learners and staff was the council’s priority and that efforts would be made to move forward as quickly as possible.

Despite those assurances, the council has not confirmed whether it expects to recover costs through warranties, insurance, or third-party liability, or whether the financial burden could ultimately fall on the public purse.

In its FOI response, the authority said releasing cost information or correspondence could prejudice commercial interests and negatively affect negotiations with contractors or other third parties. It concluded that there was a greater public interest in withholding the information than in disclosure.

The decision is likely to fuel anger among parents and residents, with many questioning how a school building less than ten years old has deteriorated to the point of requiring hundreds of emergency supports and a potential full roof replacement — and why the true cost of that failure is being kept from public view.

Pembrokeshire County Council has not said when, or if, the total cost of the works will be made public.

 

Education

Influencers amplify misinformation and online toxicity, study finds

Published

on

SOCIAL media influencers can significantly increase the spread and toxicity of misinformation online, according to new research led by academics at Cardiff Business School.

The study, published in the journal Psychology & Marketing, analysed brand-related misinformation and associated user comments across forty-seven brands in nine industries over a three-year period. Researchers say it is the first study to measure how online toxicity differs when misinformation comes from influencers rather than ordinary users.

Brands increasingly rely on social media influencers to reach audiences, with spending on influencer marketing hitting a record $33bn in 2025. While influencers can drive engagement and sales, the communities built around them can also amplify inaccurate claims and direct hostility towards brands.

The research found that regular social media users who spread misinformation are often challenged or criticised by other users. As a result, discussions tend to become more civil over time as inaccuracies are corrected.

Influencers, however, face the opposite incentive. Their visibility, engagement and profits often increase when posts generate controversy or strong emotional reactions.

The analysis found that online toxicity was particularly high when influencers discussed socio-political issues, where public emotions and stakes are greater.

Lead author Dr Giandomenico Di Domenico said: “Social media influencers often have huge followings that are extremely valuable for brands seeking to increase sales.

“But our research shows the negative consequences when influencers endorse or amplify misinformation. Under the same conditions that increase their visibility and influence, influencers also generate significantly more toxic engagement than regular users.”

He explained that the close relationships influencers cultivate with their followers play a key role.

“Unlike regular users, influencers form parasocial bonds with their communities. These relationships make followers far more likely to support or defend claims without critically questioning them.

“This means misinformation introduced within these networks does not simply attract attention — it can transform scattered reactions into collective, belief-driven antagonism.”

The researchers identified two key mechanisms that strengthen misinformation when it comes from influencers.

The first is “legitimation”, where the influencer’s endorsement lends credibility to a claim. The second is “community enmeshment”, where followers rally around the influencer and reinforce the narrative.

When combined, these factors can create what researchers describe as “toxic echo chambers”, producing a self-reinforcing cycle in which toxicity increases engagement — and engagement encourages further inflammatory content.

The study highlights how these dynamics played out in early 2025 when several TikTok influencers posted viral videos claiming luxury brands including Hermès, Louis Vuitton and Chanel secretly manufactured products in Chinese factories while marketing them as “Made in France” or “Made in Italy”.

The videos presented the claims as exposés of industry deception but offered no verifiable evidence. Despite this, they generated millions of views and fuelled widespread online debate about authenticity, ethics and transparency in the luxury industry.

Dr Di Domenico said the example illustrates a growing tension within influencer culture.

“Despite the positive impact influencers can have on marketing outcomes, their prominence also introduces new risks,” he said.

“When misleading or controversial claims are amplified by influencers, the resulting backlash can create highly toxic environments that damage brands and distort public understanding.”

The research paper, titled Don’t You Know That You’re Toxic? How Influencer-Driven Misinformation Fuels Online Toxicity, is published in Psychology & Marketing.

 

Continue Reading

Education

Manorbier school closure approved while insurance claim still unresolved

Published

on

Council confirms negotiations with insurer ongoing following 2022 fire

PEMBROKESHIRE COUNTY COUNCIL has confirmed that negotiations with its insurer over the fire that destroyed Manorbier Church in Wales VC School are still ongoing, despite councillors voting to move ahead with the process of closing the school.

The small rural school has been operating from Jameston Community Hall since the original building was badly damaged by fire in October 2022.

Last week, during a meeting of full council on Thursday (Mar 5), members voted to authorise the publication of a statutory notice to discontinue the school.

Insurance negotiations not highlighted during debate

During the council debate on Thursday (Mar 5), councillors were told that the insurance settlement offered following the fire fell “far below” the estimated cost of reinstating the school.

However, no indication was given during the meeting that negotiations with the insurer had not yet been finalised.

The council has since confirmed to the Herald that discussions over the claim are still ongoing and that the final settlement figure has not yet been agreed.

The decision means the formal closure process will now begin, with pupils expected to transfer to nearby St Florence School if the proposal ultimately goes ahead.

However, in response to questions from the Herald, the council confirmed that the insurance claim relating to the fire has not yet been finalised.

A communications officer at the Council said on Thursday (Mar 12) that negotiations with the insurer are continuing.

“The total value of the insurance settlement offered or received in relation to the Manorbier School fire – negotiations with the insurer are ongoing so we are unable to comment,” he said.

The council also confirmed that the insurance claim has not yet been settled.

Manorbier School: Destroyed by fire in October 2022 (Image: Herald File)

Rebuild costs estimated at around £2.6m

During the council debate, Cabinet Member for Education Cllr Guy Woodham told councillors that the insurance settlement offered following the fire was “far below the estimated cost of reinstating the school to a suitable operational standard.”

Feasibility work previously presented to councillors suggested the cost of rebuilding or reinstating the school building would be in the region of £2.6 million.

The council has confirmed that the insurance policy carries an excess of £200,000.

When asked whether any insurance funds had been allocated elsewhere within the council’s capital budget, the authority said none had been used.

Campaigners argued insurance should fund rebuild

Campaigners backing a rebuild of the school at a protest at County Hall (Image: Supplied)

Supporters of the school have repeatedly argued that insurance money from the fire should be used to rebuild the village school.

The consultation process attracted 252 responses, with 228 opposing the closure and only 20 supporting it.

Many parents and residents also raised concerns that the school had previously been expected to be rebuilt following the fire.

At a Cabinet meeting in March 2023 the council agreed to support the reinstatement of the school subject to feasibility work and the development of a business case.

However, the subsequent analysis concluded that rebuilding the school would not represent value for money in the context of pupil numbers and the wider school estate in the Tenby area.

Questions remain over insurance position

The confirmation that insurance negotiations are still ongoing raises further questions about the financial context surrounding the decision to close the school.

While councillors were told that the settlement offered by insurers falls “far below” the estimated cost of reinstating the school, the council has not yet disclosed the value of the insurance cover that was in place at the time of the fire.

The Herald has asked Pembrokeshire County Council to confirm the insured reinstatement value of the Manorbier School building when the fire occurred in October 2022.

If the building was insured for significantly less than the estimated rebuild cost, it could raise wider questions about insurance cover for public buildings across the county.

The Herald has therefore also asked the council to clarify whether other schools and council-owned buildings are insured at their full reinstatement value, and when those insurance valuations were last reviewed.

For now, the council says negotiations with its insurer are still taking place.

 

Continue Reading

Education

Council votes to close fire-damaged Manorbier school despite earlier rebuild hopes

Published

on

Over 90% opposed closure as insurance settlement falls short of rebuild cost

THE FUTURE of Manorbier Church in Wales VC School has been sealed after Pembrokeshire County Council voted to move forward with plans to close the school – more than three years after a fire destroyed the building and initially raised hopes it would be rebuilt.

The decision was taken during a meeting of full council on Thursday (Mar 5), where members agreed to publish a statutory notice to discontinue the school.

The move follows a consultation which revealed overwhelming opposition to closure. Of the 252 responses received, more than 90% were against shutting the school.

Cabinet Member for Education Cllr Guy Woodham

Despite that opposition, council officers recommended proceeding with closure, citing falling pupil numbers, surplus school places in the Tenby area and the financial implications of rebuilding the fire-damaged site.

Introducing the report, Cabinet Member for Education Cllr Guy Woodham acknowledged the difficult circumstances surrounding the decision.

“I want to once again thank the headteacher, governing body, staff, learners, families and the community for supporting the school so admirably during these very challenging times,” he told councillors.

The school building was severely damaged by fire in October 2022, forcing pupils and staff to relocate to temporary accommodation at Jameston Community Hall, where the school has continued operating.

Rebuild hopes raised

In the months following the fire, the council appeared to signal that rebuilding the school was the likely outcome.

In March 2023, cabinet backed what it described as “positive steps towards rebuilding” Manorbier School and approved funding for a feasibility study into reinstating the building.

Council reports at the time stated that full reinstatement of the school was the “preferred option.”

Pupils were moved to Jameston Community Hall with the expectation that the school would continue operating there while rebuilding work was completed.

However, after the feasibility work was carried out and a wider review of education provision in the area was undertaken, the council’s approach changed.

Insurance settlement shortfall

During Thursday’s debate, councillors were told the financial reality of rebuilding the school had proved more challenging than first anticipated.

Cllr Woodham said the insurance settlement offered following the fire fell “far below the estimated cost of reinstating the school to a suitable operational standard.”

That gap between the insurance settlement and the cost of rebuilding was a significant factor in the council’s reassessment of the school’s future.

Cllr Woodham also acknowledged that the earlier cabinet decision had led many residents to believe rebuilding was inevitable.

“There may have been a general perception that a decision had been made to reinstate the school,” he told the chamber.

However, he said the 2023 decision had only been to carry out feasibility work and develop a business case.

Falling pupil numbers cited

Council officers also pointed to demographic pressures affecting the wider school system in Pembrokeshire.

The authority says there has been a decline in the pupil population, alongside an increasing number of schools with surplus places.

Officials told councillors that long-term planning decisions must be based on the viability of permanent school sites rather than temporary arrangements.

Forecasts presented to the council suggested there was insufficient long-term growth in pupil numbers to sustain Manorbier School.

Community fears

Many parents and residents had argued the school remained viable before the fire and could still thrive if rebuilt.

Campaigners also raised concerns that closing the school would harm the local community and undermine efforts to attract young families to the area, particularly given recent housing developments nearby.

Transport and road safety concerns were also raised during the consultation, with some residents warning that pupils could face longer journeys on narrow rural roads if the school closed.

Church opposition

The proposal also drew objections from the Diocese of St Davids, which warned about the loss of a Church in Wales school in the area.

A letter from Bishop Dorrien Davies opposing the closure formed part of the consultation evidence presented to councillors.

Bishop Dorrien Davies visiting Manobier School’s pupils and teachers in January

Earlier this year the bishop visited pupils and staff at the school while they were based in temporary accommodation, praising the quality of teaching and pastoral care despite the difficult circumstances.

What happens next

Thursday’s decision does not immediately close the school but authorises the Director of Education to publish a statutory notice to discontinue the school.

If the process proceeds as expected, the school will eventually close and pupils will be transferred to other schools in the area.

The council has not yet confirmed the value of the insurance settlement or the estimated cost of rebuilding the school, figures which may now come under further scrutiny following the debate.

 

Continue Reading

Education5 hours ago

Manorbier school closure approved while insurance claim still unresolved

Council confirms negotiations with insurer ongoing following 2022 fire PEMBROKESHIRE COUNTY COUNCIL has confirmed that negotiations with its insurer over...

Crime1 day ago

‘Knife attack’ at Spittal property leaves man in hospital

POLICE have arrested a woman following what is being described as a ‘knife attack’ at a property in Spittal on...

Community1 day ago

Pembrokeshire to receive its first banking hub in Pembroke Dock

LINK, the UK’s Cash Access and ATM network, has today announced local people and businesses in Pembroke Dock will benefit from a new banking...

Health2 days ago

Future of Withybush Hospital petition sparks urgent call for Senedd debate

CALLS have been made for an urgent debate in the Senedd over the future of services at Withybush Hospital as...

Crime3 days ago

Man jailed after threatening to chop teen’s ears off in drunken phone call

17-year-old victim said she feared for her life after a series of threats A MAN who threatened a teenage girl...

Sport3 days ago

Sean Bowen set for historic Welsh clash at Cheltenham Gold Cup

PEMBROKESHIRE jockey Sean Bowen could be part of a historic all-Welsh showdown when he lines up in the Cheltenham Gold...

Community3 days ago

Tenby still waiting as Wales hits 50 rural mobile mast upgrades

Seaside town plagued by signal congestion again absent from latest government-backed coverage improvements A NEW milestone in the UK Government’s...

Crime4 days ago

Man raped 15-year-old girl in caravan while she was on family holiday in west Wales

Jury convicts Pendine man after court hears he raped intoxicated teenager in caravan during family holiday A MAN who raped...

Community4 days ago

Crash sparks fresh questions over future of former Haverfordwest library

CONCERNS have been raised about the future of a distinctive Haverfordwest building after a car crashed into it last week,...

Community5 days ago

Councillors vote to close Ysgol Clydau despite community concerns

Petition and protests fail to prevent closure of small rural school near Tegryn PEMBROKESHIRE COUNTY COUNCIL has voted to close...

Popular This Week